Question: A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h) per day at 100%. The resource performs actual work of 10 hours on the first day. How has the Peak for this resource changed?

  1. It has changed to 10h.
  2. It has changed to 6h.
  3. It has changed to 125%.
  4. It has changed to 110%.

Answer: The correct answer of the above question is Option C:It has changed to 125%.