Question: How do you mark a task's progress and have that progress reflected in the task's summary task?
- Use the **Task** tool on the ribbon's **Task** tab for the subtask.
- Enter a value in the %**Complete** field.
- Use the **Task** tool en the ribbon's **Task** tab for the summary task.
- Use the **Project Information** dialog box.
Answer: The correct answer of the above question is Option C:Use the **Task** tool en the ribbon's **Task** tab for the summary task.