Question: When setting the **Calculate multiple critical paths** option in a master project's **Advanced** settings, which statement is correct?
- Subprojects will have critical paths calculated individually.
- Individual resources will have critical paths calculated.
- Milestones will have critical paths fixed.
- Only one critical path will be calculated for a linked project.
Answer: The correct answer of the above question is Option A:Subprojects will have critical paths calculated individually.