Question: You are assigned the ownership of schedule comprising approximately 12,000 tasks. You need to know exactly, with detail, which tasks have a constraint other than ASAP. The most effective method do this is to create a filter that tests for which set of conditions?
- Constraint TypeSummaryRecurring% CompleteActive
- Constraint TypeSummaryRecurring% CempleteActive
- Constraint TypeDetailRecurringDurationActive
- Constraint TypeSummaryRecurring% CompleteActive
Answer: The correct answer of the above question is Option D:Constraint TypeSummaryRecurring% CompleteActive