Question: You are troubleshooting a schedule on someone else's computer The schedule has 10,000 tasks. When a change is made to a task's duration on a Fixed Units task, the start and finish dates do not change. change highlighting does not appear, and the Gantt Chart bat does not update. What is the cause of this issue?

  1. Inserted projects are calculated like summary tasks is selected.
  2. Calculate multiple critical paths is not selected.
  3. One of the Com add-ins is not selected.
  4. Calculate project after each edit is set to Off.

Answer: The correct answer of the above question is Option D:Calculate project after each edit is set to Off.