Question: You are working with subproject files (the master project file is not open) and have saved the changes you made. What happens to the master project when it is opened?
- The master project will not reflect any changes until the subproject files ate opened as well.
- The master project will display an error.
- The master project will display message stating that changes were made and the subproject files must be opened first.
- The master project will reflect the changes made to the subproject files.
Answer: The correct answer of the above question is Option D:The master project will reflect the changes made to the subproject files.