Question: You want to switch the scheduling mode for a project from scheduling from a start date to scheduling from a finish date. This action will change the default constraint from As Soon As Possible to As Late As Possible. Which dialog box should you use to make this change?
- Resource Information
- Project Information
- Task Information
- Change Working Time
Answer: The correct answer of the above question is Option B:Project Information